CERC RoPs: Petition for recoupment of under-recovered energy charges due to shortfall in energy generation Chutak Power

Application under Regulation-44(6) of CERC (Terms and Conditions of Tariff) Regulations, 2019 for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of generating station during the FY 2021-22 in respect of Chutak Power Station.

NHPC Limited

Versus

Power Development Department, J&K

Record of Proceedings

During the hearing, the learned counsel for the Petitioner pointed out that it has filed the additional information as sought by the Commission vide ROP of the hearing dated 29.