March 04,2024

GERC: Petition filed under Electricity Act, 2003 and GERC Regulations, 2005 seeks approval to levy 2.5% supervision charges instead of 15% for shifting licensee's infrastructure for national and state highway projects as per Ministry of Power's SOP

1. The matter was kept for hearing on 21.02.2024. 

 2. At the outset, Ld. Adv. Ms. Srishti Kindaria appearing on behalf of the Petitioners submitted that Pursuant to the Daily Order dated 11.01.2024 passed by the Commission the Petitioner has filed amended memo of parties with impleaded Respondent No.