Petitioner: Suzlon Global Service Limited
Versus
Gujarat Energy Transmission Corporation Ltd. & Gujarat Energy Development Agency
Background: Petition under Section 86 of the Electricity Act, 2003 read with Order No. 05/2024 dated 31.08.2024 “Tariff Framework For Procurement of Power by Distribution Licensees And Others from Wind Power Projects for the State of Gujarat” passed by the Commission seeking extension of Scheduled Date of Commissioning (SCOD) of infrastructure being developed by the Petitioner for evacuation of power from its 200 MW wind farm located at Jamjodhpur to 220kV Kalawad substation of Respondent / GETCO, on account of occurrence of Force Majeure events.