Petitioner: Uttar Haryana Bijli Vitran Nigam

The Commission observes that the developer’s obligation to create adequate infrastructure for the ultimate load persists and the inadequacy of amount ₹1.948 crore is to be cured by the Respondent No. 2 and 3. Hence, the petition is disposed off with following directions to the Respondent No.