• Infographics
  • Insights
  • Check Pricing
  • Newsletter
  • Login

Dear Patrons & Readers, 

NTPC Renewable Energy Limited

Versus

Rajasthan Electricity Regulatory Commission, Rajasthan Urja Vikas Niga,m Limited, Solar Energy Corporation of India Limited, AEW India North One Private Limited & Green Infra Wind Energy Limited

Background:

1. Assail, in this appeal, is to the order dated 31.08.2022 passed by the 1 st respondent Rajasthan Electricity Regulatory Commission (hereinafter referred to as “the Commission”) in petition no.1905/2021 whereby the Commission has refused to recognize (i) directions issued by the Hon'ble Supreme Court in Order dated 19.04.2021 (Great Indian Bustard case) requiring the power generators to install bird flight diverters, and (ii) the enhancement of Grid Connectivity Charges under the Rajasthan Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff from Renewable Energy Sources) Regulations, 2020 (hereinafter referred to as the “RERC Renewable Energy Regulations, 2020”), as Change in Law events affecting the power generators including the appellant herein.

2. The appellant had initially raised both these pleas in the appeal. However, on 21.07.2026, when the appeal had come up for hearing, learned counsel for the appellant restricted the scope of the appeal to the claim of the appellant with regards to entitlement for compensation on account of increase in Grid Connectivity Charges as a Change in Law event alone.

3. Undisputedly, the bid deadline in the instant case was 28.10.2020. At that time RERC Renewable Energy Regulations, 2015 were in force. Regulation 48 of these regulations prescribed Grid Connectivity Charges @ Rs.2 lakh per MW. Subsequently, RERC Renewable Energy Regulations, 2020 were notified on 02.11.2020. Vide Regulation 89.1 read with Regulation 48 of these regulations, the Grid Connectivity Charges were enhanced to Rs.2.5 lakh per MW. Accordingly, the appellant has paid Rs.11.75 crores towards enhanced Grid Connectivity Charges instead of Rs.9.40 crores as would have been payable in terms of RERC Renewable Energy Regulations, 2015.

4. The Commission, in the impugned order, has refused to acknowledge the increase in Grid Connectivity Charges as a Change in Law event on the ground that as per the Power Purchase Agreement (PPA) executed between the appellant and the respondent no.3 Solar Energy Corporation of India Limited (in short “SECI”), it is the responsibility of the solar power developer i.e. the appellant to obtain grid connectivity and to bear the risks as well as costs incidental to it.

5. We have heard Mr. Shri Venkatesh, learned counsel for the appellant, Mr. Amal Nair, learned counsel for the 2nd respondent and Ms. Anushree Bardhan, learned counsel for the 3rd respondent. We have also perused the written submissions filed by the learned counsels.

6. learned counsel for the appellant would argue that merely because obtaining grid connectivity was contractually the responsibility of the appellant does not mean that the statutory enhancement in the Grid Connectivity Charges would not constitute Change in Law event in terms of the PPA provisions in this regard. He submitted that RERC Renewable Energy Regulations, 2020 were notified after the bid deadline and these squarely fall within the definition of the term “law” under the PPA, which expressly includes any statute, ordinance, regulation, notification, rule or other instrument having the force of law. To buttress his submissions on this aspect, the learned counsel has relied upon the judgment of the Hon'ble Supreme Court in GMR Warora Energy Limited v. CERC and Ors. (2023) 10 SCC 401.

7. On behalf of the respondents, it is argued that the claim of the appellant with regards to increase in Grid Connectivity Charges as Change in Law event is not maintainable at all for the reason that the appellant had not raised any such claim during the proceedings before the Commission. It is pointed out that the impugned order has been passed by the Commission qua three different power generators, one of which was the appellant and the claim with respect to enhancement of Grid Connectivity Charges constituting a Change in Law event under the PPAs was raised by the other two generators on which the Commission had returned its findings in the impugned order. It is argued that the appellant cannot be permitted to raise such a claim for the first time in its appeal before this Tribunal. On merits it is argued that the Commission has rightly held that since the grid connectivity was the responsibility of the appellant and the associated risks/costs incidental to the grid connectivity were to be borne by the appellant, the increase in Grid Connectivity Charges cannot be recognized as a Change in Law event affecting the power generators. It is further pointed out that even otherwise also, the claim of the appellant is not maintainable for the reason that no notice, as required under Article 12.3 of the PPA, was served by the appellant upon the respondents. On these submissions, the learned counsels for the respondents urged us to dismiss the appeal.

8. In rejoinder, learned counsel for the appellant submitted that Article 12 of the PPA does not prescribe issuance of notice as a condition precedent for claiming relief for the Change in Law event. He would further submit that having resisted the claim of respondent nos.2 and 3 in this regard before the Commission, they are precluded from contesting the entitlement of appellant under the said Change in Law event on the technical plea of absence of notice. On this aspect, the learned counsel as relied upon the judgment of this Tribunal dated 15.09.2022 in appeal no.256/2019 & Batch M/s Parampujya Solar Energy Pvt. Ltd & Anr v. CERC & Ors. The learned counsel would also dispute the contention agitated on behalf of the respondents that the appellant had not specifically claimed the assessment of impact of Grid Connectivity Charges before the Commission.

32. It is also argued on behalf of the appellant that merely because obtaining grid connectivity was contractually the responsibility of the appellant does not mean that the statutory enhancement in these charges would not constitute Change in Law. These arguments have been advanced for the reason that the Commission has, in the impugned order, held that in terms of the PPA, the increase in Grid Connectivity Charges has to be borne by the solar power developers and their claim for declaration of increase in such charges as Change in Law cannot be accepted. Pertinently, these observations have been made by Commission on the claim made by respondent nos.4 and 5 in this regard. As already noted hereinabove, no such claim was made by the appellant before the Commission. While prima facie finding no fault in these observations of the Commission, we are of the opinion that a detailed discussion in this regard would be appropriate in the appeals, if any, filed by the respondent nos.4 and 5 against the impugned order.


Highlights from the week of
16 October 2026 to 23 October 2026

Petitioner: M/s Avtar Steel Pvt. Ltd.VersusHaryana Vidyut Prasaran Nigam (HVPNL) & Uttar Haryana Bijli Vitran Nigam (UHBVNL)Background: The present

Petitioner: The HP State Electricity Board Ltd. & The Shivalik Green Energy Solar Power ProjectBackground: This Joint Petition has been filed by the

TGREDCO [Telangana Renewable Energy Corporation Ltd] has issued RfS for Selection of RE Power Developers for Supply of 2000 MW Firm and Dispatchable Renewable Energy R

TGREDCO's 800 MW wind tender invites developers to build ISTS or Telangana STU-connected projects to supply power to TGDISCOMs under 25-year PPAs via tariff-based comp

Petitioner: Municipal Corporation of DelhiVersusBSES Rajdhani Power Ltd. & Ors.Background: Petition under Section 63, Section 86(1)(b),(e) and (k) of the

Approval under Section 62 read with Section 79(1)(d) of the Electricity Act, 2003 and under the Regulation 15(1)(a) and Regulation 23 of the Central Electricity Regula

Petitioner: Jindal Urban Waste Management (Bawana) Ltd.VersusBSES Rajdhani Power Ltd. & Ors.Background: The Petitioner, Jindal Urban Waste Management (Ba

Petition under Section 62 read with Section 79(1)(d) of the Electricity Act, 2003, and under Regulations 15 and 23 of the Central Electricity Regulatory Commission (Co

Petitioner: M/s KISHAN URJA HITKARI SAMITIVersusRajasthan Urja Vikas & IT Services Ltd (‘RUVITL’)Background: The present petition has been filed by M

Approval under Section 62 read with Section 79(1)(d) of the Electricity Act, 2003 and under Regulation 15(1)(a) and Regulation 23 of the Central Electricity Regulatory

Petitioner: Thar Power Transmission Service Limited(2385/2025), Barmer Power Transmission Service Limited(2386/2025) & Hadoti Power Transmission Service Limit

Petitioner: TPCODLVersusGRIDCO LimitedBackground: The Petitioner, M/s. TPCODL has submitted the application in compliance with the directives stipulated in t

Telangana Power Generation Corporation Limited - TGGENCO is a Government of Telangana Undertaking. This Request for Selection is issued under Ministry of Power Guideli

NTPC, on behalf of NTPC (Mauritius) Energy Limited, has invited online bids on open tender basis for an EPC package to develop a 15MWac floating solar PV project coupl

Petition seeking to surrender Category V Trading Licence in terms of Regulation 20(3) of the Central Electricity Regulatory Commission (Procedure, Terms and Conditions

Petitioner: M/s Tarini Infrastructure LimitedVersusGujarat Urja Vikas Nigam Limited, Narmada Water Resources & Gujarat Electricity Transmission Corp. LimitedBackgro

Petition under Section 16 of the Electricity Act, 2003 read with Central Electricity Regulatory Commission (Procedure, Terms and Conditions for Grant of Transmission L

Application under Sections 14 and Section 15 (1) of the Electricity Act, 2003 read with Regulation 6 of the Central Electricity Regulatory Commission (Procedure, Terms

Petitioner: M/s Vgrown Tech Pvt. LimitedVersusGujarat Energy Transmission Corp. LimitedBackground: Petition under Section 86 (1) (c), (e), (f) and o

Petition seeking approval under Section 17 of the Electricity Act, 2003 for bringing on record the appointment of Vardhman Trusteeship Private Limited as the Security

Petition for revision of tariff of Jhanor Gandhar Gas Power Station (657.39 MW) for the period from 1.4.2019 to 31.3.2024 after the truing up exercise. NTPC Limited,Ve

Maharashtra State Power Generation Co. Ltd. [MAHAGENCO], Mumbai has issued RFX No. CE/RE-P&P/500MW/BESS/2026 inviting online bids under Two-Bid System [Techno-Comm

Petitioner: Bihar Grid Company LimitedBackground: Petition for the prior approval of Work wise & Scheme wise Capital Investment Plan and Capitalization u

NTPC Renewable Energy Limited [NTPC REL], a wholly owned subsidiary of NTPC Limited, has issued Invitation for Bids [IFB] No. NRE-CS-5848-004[EPC]-9 dated 16.10.2026 f

Petitioner: TP Central Odisha Distribution Ltd. (TPCODL)VersusGRIDCO & AnotherBackground: The Petitioner, TP Central Odisha Distribution Limited ("TPCODL

Petitioner: Solar Energy Corporation of India Ltd.VersusJharkhand Bijli Vitran Nigam Limited (JBVNL) & Jharkhand Urja Sancharan Nigam Limited (JUSNL)Back

Petitioner: Tata Steel Limited (TSL) (Steel Manufacturer, for its CPP)VersusJharkhand Renewable Energy Development Agency & OrsBackground: The Petit

GRIDCO Limited, Odisha's renewable energy nodal agency under the Odisha Renewable Energy Policy 2022, has floated a tender to appoint a consultant for conducting an En

Petitioner: Photon Ojas Pvt. LimitedVersusPunjab State Power Corporation Ltd, Punjab Energy Development Agency & Syndicate Bank LimitedBackground:&n

NTPC Renewable Energy Limited [NTPC REL], a group company of NTPC Limited, has invited online bids for EPC Package with Land for Development of 900 MW ISTS Connected G

Petition for truing up of the transmission tariff for the 2019-24 tariff period and the determination of the transmission tariff for the 2024-29 tariff period for 7 No

Petitioner: Shri Ram FilamentVersusSDO Op Sub Division Sub Urban No 1 DHBVN & XEN Op City Division DHBVNBackground: Review Petition under section 94

Approval under Section 62 read with Section 79(1)(d) of the Electricity Act, 2003 and under Regulation 15(1)(a) and Regulation 23 of the Central Electricity Regulatory

Petition for the truing up of the transmission tariff for the 2019-24 tariff period and the determination of the transmission tariff for the 2024-29 tariff period for

Petitioner: M/s Avtar Steel Pvt. Ltd.VersusHaryana Vidyut Prasaran Nigam (HVPNL) & Uttar Haryana Bijli Vitran Nigam (UHBVNL)Background: The present

Application under Sections 14 and 15 (1) of the Electricity Act, 2003 read with Regulation 6 of the Central Electricity Regulatory Commission (Procedure, Terms and Con

Petitioner: Eleven Power Private LimitedVersusDakshin Haryana Bijli Vitran Nigam Limited (DHBVNL), Uttar Haryana Bijli Vitran Nigam Limited (UHBVNL) &&nb

Petitioner: M/s Dhursar Solar Power Pvt. Limited.VersusRajasthan State Load Despatch Centre,  Rajasthan Rajya Vidyut Prasaran Nigam Limited & M/s Manikar

Petitioner: West Bengal State Electricity Distribution Company Limited (WBSEDCL)Background: The West Bengal State Electricity Distribution Company Limited (W

Petitioner: West Bengal State Electricity Distribution Company Limited (WBSEDCL)Background: The West Bengal State Electricity Distribution Company Limited (W

The Haryana Power Purchase Centre (HPPC), acting on behalf of Haryana Discoms i.e. UHBVNL and DHBVNL, has issued RfS No. /HPPC/SOLAR/LTP-III/Solar & BESS dated 21.10.2

Petitioner: M/s HR Sabarmati Pvt. LimitedVersusGujarat Urja Vikas Nigam Limited & Gujarat Energy Transmission Corp. LimitedBackground: Petition und

Petitioner: CESC Limited (CESC)Background: CESC Limited (CESC) has submitted a petition under Section 94(1)(f) of the Electricity Act, 2003, read with Regula

Approval under Regulation 23 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 2023 and the Central Electricity Regulatory Commission

Approval under Section 62 read with Section 79(1)(d) of Electricity Act, 2003 and under the Regulation 15(1)(a) and Regulation 23 of the Central Electricity Regulatory

Corrigendum to order dated 13.5.2025 in Petition No. 19/TT/2025. Petition for truing up of the transmission tariff for the 2019-24 tariff period and the determination

Petitioner: India Power Corporation Limited (IPCL)Background: IPCL, a distribution licensee under the West Bengal Electricity Regulatory Commission, submitte

Petition under Section 14 of the Electricity Act, 2003 read with the Central Electricity Regulatory Commission (Procedure, Terms and Conditions for Grant of Transmissi

Petition under Section 15 (1) of the Electricity Act, 2003 read with Regulation 6 of the Central Electricity Regulatory Commission (Procedure, Terms and Conditions for

Petitioner: Haldia Energy LimitedBackground: WBERC vide Order dated 28.07.2022 in Case No. TP-92/20-21 determined the Tariff for Haldia Energy Limited (HEL)

Petitioner: Kerala State Electricity Board Limited (KSEBL)VersusNTPC LtdBackground: Petition under Regulation 77 of the KSERC (Terms and Conditions for deter

The Commission has framed the draft OERC (Procurement of Energy from Renewable Sources and its Compliance) Regulations.