• Infographics
  • Insights
  • Check Pricing
  • Newsletter
  • Login

Dear Patrons & Readers, 

Review of Commission’s order dated 10.7.2015 in Petition No.197/GT/2013 regarding approval of generation tariff for Circulating Fluidized Bed Consumption (CFBC) Technology based Barsingsar Thermal Power Plant (2x125 MW) of Neyveli Lignite Corporation Limited for the period from the COD of Units-I and II till 31.3.2014.

Neyveli Lignite Corporation Limited

Versus

Jaipur Vidyut Vitaran Nigam Ltd, Ajmer Vidyut Vitaran Nigam Ltd., Jodhpur Vidyut Vitaran Nigam Ltd & Rajasthan Urja Vikas Nigam Ltd

Background:

The Petitioner, Neyveli Lignite Corporation Limited (in short “NLCIL”), operates the Barsingsar Thermal Power Plant (in short “generating station”), based on Circulating Fluidized Bed Combustion (CFBC) technology. The generating station has an installed capacity of 250 MW, comprising two units of 125 MW each, equipped with CFBC lignitefired boilers feeding turbines, sourced from its captive mines. Units-I and II of the generating station were commissioned on 20.1.2012 and 29.12.2011, respectively.

2. Petition No. 197/GT/2013 was filed by the Petitioner seeking tariff determination for the generating station for the period from the date of commercial operation of Unit-I and II up to 31.3.2014, in accordance with the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2009 (in short “the 2009 Tariff Regulations”). The Commission, vide order dated 10.7.2015, determined the generating station’s tariff for the said period.

3. Aggrieved by the order dated 10.7.2015, the Petitioner sought review on the ground of errors apparent on the face of the record, primarily concerning the treatment of delay of 16 months for Unit-I and 18 months for Unit-II during construction up to synchronization, disallowance of delay of 21 months for Unit-I and 13 months for Unit-II between synchronization and actual COD, reduction of capital cost by ₹88.23 crore after adjustment of infirm power and fly ash sales, adjustment of liquidated damages of ₹129.88 crore based on a bank guarantee of ₹61.52 crore, incorrect computation of Interest During Construction (IDC) without considering deferred debt deployment and its implications, and arithmetical errors in the calculation of gross normative equity, gross notional loan and opening gross block in the Review Petition No. 18/RP/2015.

4. The Commission, vide order dated 14.3.2016, disposed of the Review Petition No. 18/RP/2015 and held that the time overrun from synchronization to COD would be partly allowed, with the consequences thereof to be shared equally between the Petitioner and the Respondents. With regard to IDC, the Commission held that the project cost as on COD would include IDC actually incurred or projected to be incurred up to COD in terms of Regulation 7(1)(c) of the 2009 Tariff Regulations and, accordingly, rejected the Petitioner’s claim for allowing the entire IDC of ₹114.55 crore as per RCE-I irrespective of actual debt deployment. The Commission further clarified that IDC up to SCOD was required to be calculated based on the actual deployment of loan up to SCOD and not on the IDC amount projected under RCE-I; however, while rejecting the review, NLCIL was granted liberty to furnish detailed justification, substantiating the position in this regard at the time of revision of tariff of the generating station based on truing-up exercise in terms of Regulation 6 of the 2009 Tariff Regulations.

5. Aggrieved by the above decision in the Review Petition No. 18/RP/2015, concerning the time overrun from the date of synchronization to the date of commissioning, the Petitioner filed Appeal No. 171 of 2016 before the Appellate Tribunal for Electricity (in short “APTEL”).

6. Subsequently, the Petitioner filed Petition No. 130/GT/2016 for revision of tariff (Truing-up) of the generating station for the period from the date of commercial operation of Units-I and II to 31.3.2014. The Commission, vide order dated 25.4.2017 in Petition No. 130/GT/2016, revised the tariff for the generating station for the period 2009-2014. Aggrieved by the said order dated 25.4.2017 in Petition No. 130/GT/2016, the Petitioner has preferred the Appeal No. 373 of 2017 before APTEL. Vide common judgment dated 16.6.2025 in Appeal Nos. 171 of 2016 and 373 of 2017, APTEL upheld the Commission’s order dated 14.3.2016 in Review Petition No. 18/RP/2015 and dismissed Appeal No. 171 of 2016, holding that although the delays of 16 months for Unit-I and 18 months for UnitII up to synchronization were condoned, the subsequent delays of 21 months and 13 months respectively from synchronization to COD could not be fully attributed to factors beyond NLCIL’s control and, therefore, the impact of such time overrun was rightly shared equally between NLCIL and the beneficiaries, with only 50% of the IDC/IEDC for the not condoned period being allowed. However, in Appeal No. 373 of 2017, relating to truingup for 2009-14, APTEL allowed the appeal to the extent that Commission’s treatment of fuel cost for Interest on Working Capital was contrary to Regulations 18(2) and 21(7) of the 2009 Tariff Regulations, holding that the landed cost of lignite for working capital purposes must include applicable royalty, taxes, duties and transportation costs; accordingly, Commission’s order dated 25.4.2017 was set aside to that extent. APTEL also considered NLCIL’s objections regarding alleged computational errors in IDC/IEDC, while the final operative order allowed Appeal No. 373 of 2017 only to the extent specifically concluded in the judgment. Accordingly, APTEL held that Appeal No. 171 of 2016 was devoid of merit and dismissed the same while the Commission’s order dated 14.3.2016 in Review Petition No. 18/RP/2015 was upheld, whereas the Commission’s order dated 25.4.2017 in Petition No. 130/GT/2016 was set aside to the extent indicated in the judgment regarding the consideration of lignite transfer price in the working capital Consequently, Appeal No. 373 of 2017 was allowed to the extent of the findings and directions recorded by APTEL in the said judgment.

In view of the foregoing discussion and the revised landed cost of lignite of ₹728.67/tonne allowed in accordance with Regulations 21(6) and 21(7) of the 2009 Tariff Regulations and the principles laid down by APTEL in its judgment dated 16.6.2025, the tariff for the period from the date of commercial operation of Units-I and II up to 31.3.2014 shall be revised accordingly. The amount under-recovered, after giving effect to the revised landed cost and the consequential tariff calculations approved in this order, shall be recovered or refunded, along with simple interest at the rate specified under Regulation 6(6) of the 2009 Tariff Regulations, as quoted above. Accordingly, the amount so determined shall be recovered or refunded in six equal monthly instalments, commencing within three months from the date of the issuance of order.

In view of the above findings and discussions, the directions issued by APTEL, vide judgment dated 16.6.2025 in Appeal Nos. 171 of 2016 and 373 of 2017 stand implemented. Accordingly, Petition Nos. 18/RP/2015 and 130/GT/2016 are disposed of in terms of the findings recorded hereinabove. 


Highlights from the week of
6 November 2026 to 13 November 2026

PUBLIC NOTICEIn exercise of powers conferred under clause (h) of sub-section (1) of Section 79 read with clause (g) of sub-section (2) Section 178 of the Electricity A

Approval under Section 62 read with Section 79(1)(d) of the Electricity Act, 2003 and under Regulation 15(1)(a) and Regulation 23 of Central Electricity Regulatory Com

Petition for the determination of the transmission tariff under Section 62 read with Section 79(1)(d) of the Electricity Act, 2003 and under Regulations 15(1)(a) and 2

Petition for the determination of the transmission tariff under Section 62 read with Section 79(1)(d) of the Electricity Act, 2003 and under Regulations 15(1)(a) and 2

Mahagenco Renewable Energy Ltd. [MahaGenco REL], Mumbai has issued NIT No. MREL/2026-27/300 MW land/T06 dated 06.11.2026 for Selection of Agency for Lease of 1200 acre

Petition for the determination of the transmission tariff under Section 62 read with Section 79(1)(d) of the Electricity Act, 2003 and under Regulations 15(1)(a) and 2

Approval under Section 62 read with Section 79(1)(d) of the Electricity Act, 2003 and under Regulation 15(1)(a) and Regulation 23 of Central Electricity Regulatory Com

Approval under Section 62 read with Section 79(1)(d) of the Electricity Act, 2003 and under Regulation 15(1)(a) and Regulation 23 of Central Electricity Regulatory Com

Approval under Section 62 read with Section 79(1)(d) of the Electricity Act, 2003 and under Regulation 15(1)(a) and Regulation 23 of Central Electricity Regulatory Com

Approval under Section 62 read with Section 79(1)(d) of the Electricity Act, 2003 and under Regulation 15(1)(a) and Regulation 23 of Central Electricity Regulatory Com

Approval under Section 62 read with Section 79(1)(d) of the Electricity Act, 2003 and under Regulation 15(1)(a) and Regulation 23 of Central Electricity Regulatory Com

Karnataka Power Corporation Limited (KPCL) has invited bids for the development, ownership, operation and maintenance of 1,000 MW (AC) of ground-mounted Solar PV capac

SPML Infra Limited (NSE: SPMLINFRA, BSE: 500402) has secured a ₹186.41 crore order from Power Grid Corporation of India Limited (POWERGRID) for extension of the 765/

NTPC Green Energy Limited (NGEL), a subsidiary of NTPC Limited, has invited online bids through Domestic Competitive Bidding for the Balance of System (BOS) Package fo

Reliance Industries has received a major boost in its solar manufacturing portfolio with the 14th revision of the Approved List of Models & Manufacturers (ALMM-II) for

Gujarat Urja Vikas Nigam Limited (GUVNL) has invited bids for procurement of power from 250 MW of grid-connected wind power projects under Phase XII, with a greenshoe

NTPC Green Energy Limited (NGEL), a subsidiary of NTPC Limited, has issued an Invitation for Bids (IFB) for Supply of Battery Containers and Grid-Forming PCS for 10 GW

Approval under Section 62 read with Section 79(1)(d) of the Electricity Act, 2003 and under Regulation 15(1)(a) and Regulation 23 of Central Electricity Regulatory Com

Petition under Section 16 of the Electricity Act, 2003 read with the Central Electricity Regulatory Commission (Procedure, Terms and Conditions for Grant of Transmissi

Petition under Regulations 10 & 18 of CERC (Terms and Conditions for Renewable Energy Certificates for Renewable Energy Generation) Regulations, 2022 for the grant of

The Ministry of Power has approved a proposal allowing renewable energy (RE) projects awarded through tenders issued by Renewable Energy Implementing Agencies (REIAs)

Corrigendum to the order dated 21.7.2026 in Petition No. 361/MP/2023. Petition under Sections 62 and 79(1)(a) of the Electricity Act, 2003, read with Regulation 29 of

Petition under Sections 17(3) and 17(4) of the Electricity Act, 2003 for creation of security interest over all the movable and immovable assets of the Petitioner in f

Petition under section 17(3) and 17(4) of the electricity act, 2003 read with regulation 6(8) of the central electricity regulatory commission (procedure, terms and co

This RfS, issued by NHPC Limited on behalf of Bundelkhand Saur Urja Limited (BSUL), invites selection of a Battery Energy Storage System Developer (BESSD) to set up co

NOTIFICATIONIn exercise of the powers conferred by sub-section (1) of Section 178 and clause (ze) of sub-section (2) of Section 178 read with clause (47) of Section 2,

The Ministry of Power has proposed extending the Electricity (Late Payment Surcharge and Related Matters) Rules, 2022 to standalone Energy Storage System (ESS) provide

The Ministry of Power has revised the Tariff-Based Competitive Bidding (TBCB) guidelines for procurement of power from grid-connected wind-solar hybrid projects, updat

The Ministry of Power has proposed the National Electricity Data Sharing Framework, 2026 to standardise electricity sector data and enable secure sharing among utiliti

The Commission has framed the draft OERC (Procurement of Energy from Renewable Sources and its Compliance) Regulations.